Unit Testing
Entry Criteria
• Development of the particular component is completed • Specifications for product are complete and approved • All test cases are documented
Exit Criteria
• All test cases completed successfully • No outstanding critical defects • All test results have been documented
System Testing
Entry Criteria
• Unit Testing has been completed • Development has been completed on the entire product • Specifications for the product have been completed and approved • All Test cases are documented
Exit Criteria
• All test cases completed successfully • All defect recorded in Test director • No outstanding critical defects • All test results have been documented • All code has been migrated into the model environment
System Integration Testing
Entry Criteria
• Unit and System testing has been completed and signed-off • All code and applications are present in the model environment • SIT test plan is approved • All test cases have been documented and approved
Exit Criteria
• No outstanding critical defects, unless agreed by UAT manager • Less than 10 major defects outstanding • All Test cases have been complete SIT summary report has been approved • SIT sign-off meeting attended by SIT manager, UAT manager/Test principal and project manager where • SIT results and finding are presented and a decision to move forward has been made
User Acceptance Testing
Entry Criteria
• The application works functionally as defined in the specifications • No high category defects outstanding • All areas have had testing started on them unless pre agreed by UAT manager/Test principal, SIT manager and Project managers • Entire system functioning and all new components available unless previously agreed between UAT manager/Test Principal, SIT manager and project managers • All test cases are documented and reviewed prior to the commencement of UAT
Exit Criteria
• No outstanding critical defects • Minimal outstanding medium category defects with plans in place to fix • 90% of Business process is working • All critical Business processes are working • All test results recorded and approved • UAT test summary report documented and approved • UAT close off meeting held.
------------- SivaPrasad
|