Hi All,
I want to know, how usually testing project estimates happen?
Are there any specific tools available or is it fully depends on company internal process.
|
Replies:
Posted By: Megha
Date Posted: 27Apr2007 at 5:37am
To some extent it does depend on what processes your company has in place but I will give a
few generic guidelines on what happens.
Estimates for testing are usually a subset of estimates for the complete project and may be
negotiable with the Project manager.
To develop estimates
- identify the tasks you will be doing
- you may have to guesstimate the expected number of test cases/scenarios - this is done
based on experience and historical data. Most estimates are required before you will know
this.
- using experience, historical data or a simple set of guidelines identify the estimated
hours for each set of tasks.
- the total for these is the estimate
On some projects you are required to re-estimate at different times when you have more
knowledge and details of the project.
|
|