test effort Estimations industry standards
Printed From: One Stop Testing
Category: Quality Assurance @ OneStopTesting
Forum Name: Estimation and Planning
Forum Discription: Estimation and Planning are two of the most integral components of product development process.Proper planning prevents a project deviate from its desired goals.
URL: http://forum.onestoptesting.com/forum_posts.asp?TID=1034
Printed Date: 24Dec2024 at 7:37am
Topic: test effort Estimations industry standards
Posted By: Anuja
Subject: test effort Estimations industry standards
Date Posted: 27Apr2007 at 1:52am
Going through the forums i understand a bit of estimations now ,but still i do have some queries 1.When
people say for full SDLC project the testing effort is about 30-35%
percent of development effort .So in that 30 %of time is all testing
included i.e Unit ,intergration ,system,performance and acceptance ) 2.How to estimate time for Knowledge transfer/transition or requirement familiarization .(Is this time is included in 30%) 3.Lastly
i want to know the industry standards for the %time required for unit
testing ,integration testing ,functional testing ,performance testing
within that 30% time 4. Also the % time required for the activites like test case writing,execution,rework and review
|
Replies:
Posted By: Megha
Date Posted: 27Apr2007 at 5:32am
Going through the forums i understand a bit of estimations now ,but still i do have some
queries
Quote:
1.When people say for full SDLC project the testing effort is about 30-35% percent of
development effort .So in that 30 %of time is all testing included i.e Unit ,intergration
,system,performance and acceptance )
When I provide estimates for testing it is usually QA and UAT, and these are provided
separately. I do not use the 30% but if I did it would be for those 2 items. Unit and
integration testing, IMO, are part of the developer estimates.
Quote:
2.How to estimate time for Knowledge transfer/transition or requirement familiarization
.(Is this time is included in 30%)
My estimates allow time for familiarization with the requirements.
[quote[
3.Lastly i want to know the industry standards for the %time required for unit testing
,integration testing ,functional testing ,performance testing within that 30% time
4. Also the % time required for the activites like test case writing,execution,rework and
review
|
|