Print Page | Close Window

QA time through the SDLC

Printed From: One Stop Testing
Category: Quality Assurance @ OneStopTesting
Forum Name: Estimation and Planning
Forum Discription: Estimation and Planning are two of the most integral components of product development process.Proper planning prevents a project deviate from its desired goals.
URL: http://forum.onestoptesting.com/forum_posts.asp?TID=1264
Printed Date: 19Dec2024 at 4:45pm


Topic: QA time through the SDLC
Posted By: Romila_luv
Subject: QA time through the SDLC
Date Posted: 05May2007 at 4:59am

Just for give you a quick response, the following is my stats overview:

. QA-Small Project: less than 2% of total effort.
. QA-Medium/Big: 2 to 3% of total effort.

QA is not Testing:

. System/Acceptance Testing effort: 7 to 20% of total effort.
. System/Acceptance Testing mean duration: 4 weeks.
. Stress Test duration: 5 to 7 weeks (time box).


Finally, QA activities impacts in QA effort estimation. First of all, you must to know wich QA activities you'll develop and who'll the participants. These activities may be permanent or by deriverables.




Print Page | Close Window