Posted By: Arati
Subject: Estimation - Testing Phase in Life cycle
Date Posted: 27Apr2007 at 2:11am
Hi members

Any guess

Roughly speaking what percentage can testing phase takes (on basis of time) in a waterfall model



Replies:
Posted By: Namrata
Date Posted: 27Apr2007 at 5:45am
There is another simple way that is (sadly) often used in software projects to compute the

time for the testing phase: it just take the time remaining after coding is finished and

before the scheduled delivery deadline of the project. Example: for a 6 (elapsed) months

project, if programming finish after 5 months, then testing takes only 1 month, so around

17% of the project