Quote sivaprasadt Replybullet Topic: Entry Criteria - Exit Criteria
    Posted: 22Jan2008 at 12:13am
Unit Testing

Entry Criteria

• Development of the particular component is completed
• Specifications for product are complete and approved
• All test cases are documented

Exit Criteria


• All test cases completed successfully
• No outstanding critical defects
• All test results have been documented

System Testing

Entry Criteria

• Unit Testing has been completed
• Development has been completed on the entire product
• Specifications for the product have been completed and approved
• All Test cases are documented

Exit Criteria

• All test cases completed successfully
• All defect recorded in Test director
• No outstanding critical defects
• All test results have been documented
• All code has been migrated into the model environment

System Integration Testing

Entry Criteria

• Unit and System testing has been completed and signed-off
• All code and applications are present in the model environment
• SIT test plan is approved
• All test cases have been documented and approved

Exit Criteria

• No outstanding critical defects, unless agreed by UAT manager
• Less than 10 major defects outstanding
• All Test cases have been complete
 SIT summary report has been approved
• SIT sign-off meeting attended by SIT manager, UAT manager/Test principal and project manager where
• SIT results and finding are presented and a decision to move forward has been made


User Acceptance Testing


Entry Criteria

• The application works functionally as defined in the specifications
• No high category defects outstanding
• All areas have had testing started on them unless pre agreed by UAT manager/Test principal, SIT manager and Project managers
• Entire system functioning and all new components available unless previously agreed between UAT manager/Test Principal, SIT manager and project managers
• All test cases are documented and reviewed prior to the commencement of UAT

Exit Criteria

• No outstanding critical defects
• Minimal outstanding medium category defects with plans in place to fix
• 90% of Business process is working
• All critical Business processes are working
• All test results recorded and approved
• UAT test summary report documented and approved
• UAT close off meeting held.
SivaPrasad



Post Resume: Click here to Upload your Resume & Apply for Jobs

IP IP Logged
Post Reply Post New Topic
Printable version Printable version

Forum Jump
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot delete your posts in this forum
You cannot edit your posts in this forum
You cannot create polls in this forum
You cannot vote in polls in this forum



This page was generated in 0.172 seconds.
Vyom is an ISO 9001:2000 Certified Organization

© Vyom Technosoft Pvt. Ltd. All Rights Reserved.

Privacy Policy | Terms and Conditions
Job Interview Questions | Placement Papers | Free SMS | Freshers Jobs | MBA Forum | Learn SAP | Web Hosting