Purpose of Job
BSP has a large portfolio of projects distributed over 4 main Assets, both
green field as well as many brown field and rejuvenation projects.
In 2006 it was
decided to set up a separate organisation for the execution of all Major
projects in BSP
to improve project delivery. The largest and one of the most challenging
major projects is the Champion Waterflood project. This project has recently
passed DG3 and needs competent engineers. The project covers the design,
fabrication and installation of a multitude of platforms and related
pipelines, power cables and umbilicals as well as upgrade and extension of
many existing facilities.
Projects in BSP
are typically executed under BSP management i.e. all design, fabrication,
procurement and installation works were done
in house or under
BSP direct supervision and therefore a very hands on approach is required.
Fabrication is executed under a frame agreement
in BSP’s own
fabrication yard in
Kuala Belait.
The primary role for this
position to provide QA/QC support during the Champion Waterflood execution
phases and work with the asset teams to build the required capability to
operate the facilities. This role includes the following:
• Provide support to PE for VAR 4 Approval § Prepare and Maintain Project
Quality Plan
• Assist in the
preparation of Project Execution and Project Assurance Plan
• Contributory member of the Project Assurance process e.g. PHC, PERT,
Audits
• Carry out QA in
SCM i.e. Supplier Evaluation, Technical Bid Evaluation, P/O Review
• Act as Focal Point for any Third Party Inspection (TPI) as required
• Attend Kick of Meetings at Vendor premises as required
• Conduct and report on Audit findings and their close out
• Monitor and control the disposition of contractor / company NCR
• Provide accurate weekly status reports on Project QA/QCS § Carry out the
requirements of Construction Completion and Pre-commissioning against the
requirements of BSP 12 Procedures
• Ensure that the Quality Records (QCDP) is available from the contractors
to support declaration of mechanical completion across the discipline using
the completion certificate
• Monitor the close out of any construction NCR, TQ and Punch list (PL) or
Outstanding work list (OWL)
• Ensure As-Built fabrication drawings are available as part of completion
and any third party verification reports issued
• Facilitate the Continuous Improvement Process using Lessons Learnt
• Contribute to the process of Project Handover to Operations and Close out
of Project
• To liaise with the corporate and contractor’s / supplier’s QA/QC resources
to ensure all the project’s quality and schedule objectives are met, whilst
maintaining a balance with cost objectives.
• Establish, review and approve quality assurance and control procedure and
monitor its implementation and see to its proper application
Purpose of Job
BSP has a large portfolio of projects distributed over 4 main Assets, both
green field as well as many brown field and rejuvenation projects.
In 2006 it was
decided to set up a separate organisation for the execution of all Major
projects in BSP
to improve project delivery. The largest and one of the most challenging
major projects is the Champion Waterflood project. This project has recently
passed DG3 and needs competent engineers. The project covers the design,
fabrication and installation of a multitude of platforms and related
pipelines, power cables and umbilicals as well as upgrade and extension of
many existing facilities.
Projects in BSP
are typically executed under BSP management i.e. all design, fabrication,
procurement and installation works were done
in house or under
BSP direct supervision and therefore a very hands on approach is required.
Fabrication is executed under a frame agreement
in BSP’s own
fabrication yard in
Kuala Belait.
The primary role for this
position to provide QA/QC support during the Champion Waterflood execution
phases and work with the asset teams to build the required capability to
operate the facilities. This role includes the following:
• Provide support to PE for VAR 4 Approval § Prepare and Maintain Project
Quality Plan
• Assist in the
preparation of Project Execution and Project Assurance Plan
• Contributory member of the Project Assurance process e.g. PHC, PERT,
Audits
• Carry out QA in
SCM i.e. Supplier Evaluation, Technical Bid Evaluation, P/O Review
• Act as Focal Point for any Third Party Inspection (TPI) as required
• Attend Kick of Meetings at Vendor premises as required
• Conduct and report on Audit findings and their close out
• Monitor and control the disposition of contractor / company NCR
• Provide accurate weekly status reports on Project QA/QCS § Carry out the
requirements of Construction Completion and Pre-commissioning against the
requirements of BSP 12 Procedures
• Ensure that the Quality Records (QCDP) is available from the contractors
to support declaration of mechanical completion across the discipline using
the completion certificate
• Monitor the close out of any construction NCR, TQ and Punch list (PL) or
Outstanding work list (OWL)
• Ensure As-Built fabrication drawings are available as part of completion
and any third party verification reports issued
• Facilitate the Continuous Improvement Process using Lessons Learnt
• Contribute to the process of Project Handover to Operations and Close out
of Project
• To liaise with the corporate and contractor’s / supplier’s QA/QC resources
to ensure all the project’s quality and schedule objectives are met, whilst
maintaining a balance with cost objectives.
• Establish, review and approve quality assurance and control procedure and
monitor its implementation and see to its proper application
Dimensions
Budget The Champion Field
is the largest field in
the East Asset Unit and one of the largest
in BSP. It is a
geologically complex field containing some 30 fault blocks and more than 500
reservoirs and has been producing since the early ‘70s. Though with a long
production history and the first water injection scheme implemented
in the mid ‘80s,
recovery from the field has remained less than 30%. The implementation of
water injection in
Block 13/14 and the de-bottlenecking of the existing WI plant over the last
2 years aimed at providing an injection capacity of 20,000 m3/d marked the
start of a commitment to pursue secondary recovery
in the Champion
Field. Over the next 5 years, it is planned to significantly expand the
field development in
Champion so that recovery can be maximised and the development plan
optimised and in
full synergy with the different areas of the field as well as other fields
within the asset unit. This project will be one of the most important
projects in BSP
forthcoming business plan and is of significant strategic importance to both
shareholders (Shell and Brunei government) from the perspective of achieving
the aspired Reserves Replacement as well as sustaining BSP’s production.
The project value is in
excess of 4 Billion BND.
Subordinates No direct subordinates.
Others
Principal accountabilities
The QA/QC Engineer has the
following responsibilities for the Champion Waterflood project:
• Assist
in developing and
maintaining PQPs comprising of project objectives, project plan, resources,
roles & responsibilities, identification of critical activities, defined
standards, process controls, audit & review plan, lesson learnt,
documentation control, inspection and certification requirements covering
all project phases and all contractors / suppliers.
• Assist in
preparing/scheduling/executing quality audit/review and follow up corrective
programmes to verify compliance with the Project’s PQP and agreed
contractors/suppliers PQP.
• To prepare and monitor compliance plan covering statutatory / legislative
requirements to ensure submission to relevant authorities for such approvals
is timely and successful.
• Coordinate with the contractors on matters of Quality Plan submittal,
documentation and the resolution of non-conformance
• Ensure the Project Change Management process is fully implemented
in the project
across all disciplines and project phases
• Ensure the inclusion of quality requirements
in
tenders/contracts/requisitions and evaluate tenders and requisitions against
quality requirements.
• Ensure that necessary inspection requirements have been included
in the Inspection
& Test Plan for inspector’s work.
• Supervise the receiving, inspection and
testing of
material and equipment as required by the Quality Plan and
in accordance
with the contract agreement prior to receipt and or acceptance by the
Company.
Main Contacts • Internally:
• The project team at all levels, plus the supporting organizations within
BSP departments e.g. Engineering section (EEN), Development (EPE),
Operational & Maintenance (EOP), Drilling-TSW, Central Engineering –SEN,
Supply / Contract Services- SCM and Construction –SCO. Operations -OPM.
• Within group: Service providers
• Externally: Main execution Contractors, Vendors, PU and other government
Qualifications
Required Degree in
relevant engineering discipline
Preferred
Competence Required
Experience The candidate must be a skilled and
experienced
professional.
• Bachelor of Science in
Engineering with min 8 years
in the oil and
gas industry in
QA/QC, inspection and auditing. Experience should include involvement
in the
fabrication and installation of offshore oil & gas facilities and working
with project engineers and contractors, auditing and involvement
in ISO
certification, review and auditing.
• Effective communication, interpersonal and leadership / influencing
skills.
• Should be computer literate and skilled user of MS Office suite of
programs and other relevant software.
Special Abilities • The
incumbent should be capable of working under considerable pressure whilst
maintaining the ability to plan, co-ordinate, motivate and direct people.
• Full understanding of HSE management principles.
• Must have a proven delivery track record.
• Have good interpersonal skills - ability to work with multidisciplinary,
multicultural teams
• Have good communication skills - ability to communicate well, laterally
and vertically within an organization.
• Have good understanding of ORP processes and the ability to promote these
into the execution.