Message Icon Topic: steps involved in Testing Databases

Post Reply Post New Topic
Author Message
Mithi25
Senior Member
Senior Member
Avatar

Joined: 23Jun2009
Online Status: Offline
Posts: 288
Quote Mithi25 Replybullet Topic: steps involved in Testing Databases
    Posted: 02Aug2009 at 11:41pm
HTML clipboard

steps involved in Testing Databases

 

Database testing primarily involves two key activities like:

A) Organising Sandboxes

B) Developing Test Cases
 

Now let us discuss these two key activities in detail

A) Key Activity - 1: Organising Sandboxes: Database testing involves the need of a copy of databases which are called sandboxes. These sandboxes are of following three types

1) Functionality Sandbox:
In this we check the new functionality of database and refactor the existing functionality. Then we pass the tested sandbox to the next stage, which is integrated sandbox.

2) Integrated Sandbox: In this we integrate all the sandboxes and then test the system.

3) QA sandbox: After the system is tested, sandboxes are sent for acceptance testing. This will ensure the quality of the database.

 

B) Key Activity - 2: Development of test cases: The step by step procedure for the development of test cases is as under:

Step - 1: Setting up of the test cases: Set up the database to a known state.

The sources of test data are

1) External test data.

2) Test scripts.

3) Test data with known values.

4) Real world data.

Step - 2: Running the test cases : The test cases are then run. The running of the database test cases is analogous to usual development testing.

Traditional Approach of Test Case Execution:

Test cases are executed on the browser side. Inputs are entered on web-input forms and data i submitted to the back-end database via the web browser interface. The results sent back to the browser are then validated against expected values.

Advantages of Traditional Approach: It is simple and no programming skill is required. It not only addresses thi functionality of stored procedures, rules, triggers and data integrity but also the functionality of application as a whole.

Disadvantages of Traditional Approach:

1) Sometimes the results sent to the browser after test case execution do no necessarily indicate that the data itself is properly written to a record in the table.

2) When erroneous results are sent back to the browser after the execution of test cases, it doesn't necessarily mean that the error is a database error.

3) A crucial danger with database testing and with regression testing in specific is coupling between tests. If we put the database in to a known state, run several tests against that known states, before setting it, then those tests are potentially coupled to one another.

Advanced Approach of Test Case Execution:

First of all we need to do a schematic preparation for Database Testing, which involves:

Generate a list of database tables, stored procedures, triggers, defaults, rules and so on. This will help us to have a good handle on the scope of testing required for database testing.

Thereafter we can follow the following points:
 

1. Generate data schemata for tables. Analyzing the schema will help us determine the following:

# Can a certain field value be Null?

# What are the allowed or disallowed values?

# What are the constraints?

# Is the value dependent upon values in another table?

# Will the values of this field be in the look-up table?

# What are user defined data types?

# What are primary key and foreign key relationships among tables?
 

2. At a high level, analyze how the stored procedures, triggers, defaults and rules work. This will help us determine the following:

# What is the primary function of each stored procedure and trigger? Does it read data and produce outputs, write data or both?

# What are the accepted parameters?

# What are the return values?

# When is the stored procedure called and by whom?

# When is a trigger fired?

3. Determine what the configuration management process is. That is how the new tables, stored procedures, triggers and such are integrated.

Step - 3: Checking the results: Actual database test results and expected database test results are compared in this step as described in the following example.

CREATE FUNCTION f_is leapyear (@ ai_year small int)

RETURNS small int

AS

BEGIN

-if year is illegal (null or -ve ), return -1

IF (@ ai_year IS NULL) or

(@ ai_year <=0) RETURN -1

IF (((@ ai_year % ) = 0) AND

((ai_year % 100) <> 0)) OR

((ai_year % 400) = 0)

RETURN 1 -leap year

RETURN 0 - Not a leap year

END

Following test cases are derived for the above piece of code:
 

Test_id

Year (Year to Test)

Expected Result

Observed Result

Match

1

-1 -1 -1 Yes

2

-400 -1 -1 Yes

3

100 0 0 Yes

4

1000 0 0 Yes

5

1800 0 0 Yes

6

1900 0 0 Yes

7

2010 0 0 Yes

8

400 1 1 Yes

9

1600 1 1 Yes

10

2000 1 1 Yes

11

2400 1 1 Yes

12

4 1 1 Yes

13

1204 1 1 Yes

14

1996 1 1 Yes

15

2004 1 1 Yes
 




Post Resume: Click here to Upload your Resume & Apply for Jobs

IP IP Logged
Post Reply Post New Topic
Printable version Printable version

Forum Jump
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot delete your posts in this forum
You cannot edit your posts in this forum
You cannot create polls in this forum
You cannot vote in polls in this forum



This page was generated in 0.595 seconds.
Vyom is an ISO 9001:2000 Certified Organization

© Vyom Technosoft Pvt. Ltd. All Rights Reserved.

Privacy Policy | Terms and Conditions
Job Interview Questions | Placement Papers | Free SMS | Freshers Jobs | MBA Forum | Learn SAP | Web Hosting