Active TopicsActive Topics  Display List of Forum MembersMemberlist  CalendarCalendar  Search The ForumSearch  HelpHelp
  RegisterRegister  LoginLogin


 One Stop Testing ForumQuality Assurance @ OneStopTestingEstimation and Planning

Message Icon Topic: Difference between Time and Effort Estimation

Post Reply Post New Topic
Author Message
Anju
Newbie
Newbie
Avatar

Joined: 27Apr2007
Online Status: Offline
Posts: 1
Quote Anju Replybullet Topic: Difference between Time and Effort Estimation
    Posted: 27Apr2007 at 1:29am
Can somebody explain me the difference between Time and effort estimation.

Time estimation: It is the time (in hours) for each task/functional point.
Effort Estimation: It is the total bandwidth each engineer has dedicated towards a project or task within the same project.

Is the skill level play any role in differentiating between time and effort estimation?



Post Resume: Click here to Upload your Resume & Apply for Jobs

IP IP Logged
Lipika
Newbie
Newbie
Avatar

Joined: 27Apr2007
Online Status: Offline
Posts: 1
Quote Lipika Replybullet Posted: 27Apr2007 at 3:54am
Skill definitively play a role when defining the effort (man/days) needed. Be careful that

the two components are not completely separated. If a development effort of 30 days is split

between 3 developers, you could need to add additional coordination activities, thus

increasing the initial effort.

IP IP Logged
Post Reply Post New Topic
Printable version Printable version

Forum Jump
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot delete your posts in this forum
You cannot edit your posts in this forum
You cannot create polls in this forum
You cannot vote in polls in this forum



This page was generated in 2.500 seconds.
Vyom is an ISO 9001:2000 Certified Organization

© Vyom Technosoft Pvt. Ltd. All Rights Reserved.

Privacy Policy | Terms and Conditions
Job Interview Questions | Placement Papers | Free SMS | Freshers Jobs | MBA Forum | Learn SAP | Web Hosting